The lesson from Walham
The severe flooding at Walham in Gloucestershire in 2007 showed UK Power Networks what temporary barriers could do.
At Walham, water surrounded a National Grid switching station, but a rapidly deployed Geodesign barrier, together with pumps, stopped the water entering the switching rooms through underground cable ducts – and 600,000 people kept their electricity.
From warning to deployment
John Gibbs, Contingency Planning Manager at UK Power Networks, explained how the company prepares:
“We subscribe to the Environment Agency Flood Warning Direct System, which sends us an email about a substation at risk. We then liaise with the flood Information duty officer in the Environment Agency, who informs us of the substations of highest concern.”
Bill Blackburn, Area Manager for Sussex, described what happens next:
“At a severe flood warning, we would start to make preparations to erect the barrier. It would probably take about three to four hours to protect a large site like this. A significant consideration is how much notice we have, determining if we have ample time to secure the whole site or if we should primarily focus on the most vulnerable parts.”
Why a temporary barrier suits substations
Building a sandbag wall to a height of 1.25 m would mean moving tonnes of sand. A Geodesign Heavy Duty C122 barrier – galvanised steel supports, horizontal connection rods and aluminium sheets – can be ready within a few hours. That matters for a company with around 300 primary substations, including some in flood-prone areas such as Hertfordshire.
Once the frame is up, it is covered with a polypropylene membrane held down by chains and clips, which seals against seepage.
The barrier was also deployed during a December storm surge at the Great Yarmouth substation in Norfolk. The predicted flood did not arrive, but the site was protected in time.
Working with other agencies
During flood emergencies, UK Power Networks works with the Environment Agency, the police and the fire service. The company serves 8 million customers across East Anglia, London and the South East, and stresses the need to prepare early. Property owners whose homes are threatened by flooding are advised to switch off electricity at the mains if it is safe to do so and to contact UK Power Networks through its emergency channels.
Lessons for network operators
- Connect warnings to action. An automatic warning service tells you which site is at risk – see flood monitoring and lead time.
- Know your installation time. Three to four hours for a large site determines how early you must start.
- Prioritise when time is short. Decide in advance which parts of a site to protect first.
To plan protection for your own substations, arrange a site assessment.