Government Agencies
Netherlands
Emergency Dike Built with Elemental E51 Barriers Protects Roermond Apartments
After heavy rainfall on 24 May 2024, Waterschap Limburg built a 150-metre emergency dike beside the Dennemarkenhof apartment complex in Roermond, the Netherlands, using Geodesign Elemental E51 barriers.
Read more
United Kingdom
River Severn Flooding: Heavy Duty Barriers Hold the Line at Ironbridge
River Severn flooding in early January 2024 tested the temporary flood defences in Ironbridge, Shropshire, where the Environment Agency had set up Geodesign barriers along the Wharfage.
Read more
United Kingdom
Oxford Flooding After Storm Henk: Temporary Barriers in Focus During PM’s Visit
On 7 January 2024, UK Prime Minister Rishi Sunak visited Oxford, where high river levels had returned, to see the impact of the flooding that followed Storm Henk.
Read more
Australia
Flood Levee Under Pressure: Charleville’s Temporary Barrier in the 2012 Warrego River Flood
In February 2012, as the Warrego River rose towards Charleville again, a quickly installed Geodesign temporary barrier worked alongside the town's levee, and the defences held.
Read more
Australia
Charleville Floods 2008: How an Overnight Temporary Levee Held Back the Warrego River
Known locally as "the levee", a Geodesign temporary barrier held back the Warrego River at Charleville in January 2008 and became a symbol of the town's response.
Read more
United Kingdom
Ironbridge Flooding 2020: Heavy Duty Barriers Through Three Storms
In February 2020, storms Ciara, Dennis and Jorge sent the River Severn to severe levels at Ironbridge in Shropshire, testing the Environment Agency's Geodesign barriers on the Wharfage.
Read more
United Kingdom
Bewdley Flood Defences: Temporary Barriers at Beales Corner in 2020
In February 2020, the River Severn at Bewdley rose close to its record level and overtopped the Environment Agency's Geodesign temporary barriers at Beales Corner, showing what happens beyond a barrier's design height.
Read more
United Kingdom
Romsey Flooding 2020: Around 800 m of Industrial P101 Barrier Deployed
Around 800 m of Geodesign Industrial P101 barrier was deployed in Romsey, Hampshire, in February 2020 to protect homes and businesses from the River Test as heavy rain hit the town.
Read more
United Kingdom
Godalming Flooding: Temporary Barrier Closes the Gap at Catteshall Bridge
In February 2020, a 7.8 m Geodesign Heavy Duty C122 barrier across Catteshall Bridge in Godalming, Surrey, closed the road gap in the town's permanent flood alleviation scheme while water levels were high.
Read more
United Kingdom
Storm Dennis: Soldiers and Agencies Build a 700 m Flood Barrier in Ilkley
As Storm Dennis approached in February 2020, soldiers, Bradford Council and the Environment Agency put up a 700 m Geodesign Industrial P101 temporary barrier in Ilkley ahead of the River Wharfe's expected peak.
Read more